Effective Use of MRP and Other Dependent Demand Models Does

Question 104

Multiple Choice

Effective use of MRP and other dependent demand models does NOT require which of the following?


A) master production schedule
B) bill of materials
C) inventory availability
D) lead times
E) cost of individual components