Which of the following statements is TRUE regarding the master production schedule?
A) It specifies what is to be made and how.
B) The schedule is independent of the aggregate plan.
C) It disaggregates the aggregate plan.
D) The master production schedule sets the upper and lower bounds on the aggregate plan.
E) It specifies the work-shift schedule for the assembly line workers.
Correct Answer: