Multiple Choice
Which of the following statements is TRUE about pegging?
A) It traces downward in the BOM from the parent item to the component.
B) It causes system nervousness.
C) It allows a segment of the master schedule to be designated as "not to be scheduled."
D) It allows the production planner to determine the cause for the requirement and make a judgment about the necessity for a change in the schedule.
E) It is an excellent tool for make-to-order environments.
Correct Answer:

Verified
Correct Answer:
Verified