Multiple Choice
The objective of layout strategy is to:
A) minimize cost.
B) develop an effective and efficient layout that will meet the firm's competitive requirements.
C) maximize flexibility.
D) minimize space used.
E) maximize worker satisfaction.
Correct Answer:

Verified
Correct Answer:
Verified
Q264: The typical goal used when developing a
Q265: _ avoids placing materials or supplies in
Q266: Which of the following is a disadvantage
Q267: The minimum number of workstations depends upon
Q268: What are three disadvantages of work sampling?
Q270: Product-oriented layouts tend to have high levels
Q271: There are three work centers (A, B,
Q272: A process layout problem consists of 3
Q273: One guideline for determining the arrangement and
Q274: "A special arrangement of machinery and equipment