Multiple Choice
Four hundred and eighty minutes of production time are available per day. The schedule calls for the production of 60 units per day. Each unit of the product requires 30 minutes of work. What is the theoretical minimum number of workstations?
A) 2
B) 3
C) 4
D) 5
E) 6
Correct Answer:

Verified
Correct Answer:
Verified