A Firm Operates a Flow Shop Building Kitchen Cabinetry for Recreational

Question 186

Essay

A firm operates a flow shop building kitchen cabinetry for recreational vehicles. The major activities of this process are listed below.
A firm operates a flow shop building kitchen cabinetry for recreational vehicles. The major activities of this process are listed below.    (a) Draw the appropriate network for this project. (b) What would the cycle time be if the goal is to produce 30 units per month (the plant operates 180 hours per month)? (c) What is the theoretical minimum number of workstations needed? (d) Balance with the most following tasks heuristic. What tasks are assigned to which stations? (e) What is the efficiency of the line obtained in part d? (a) Draw the appropriate network for this project.
(b) What would the cycle time be if the goal is to produce 30 units per month (the plant operates
180 hours per month)?
(c) What is the theoretical minimum number of workstations needed?
(d) Balance with the most following tasks heuristic. What tasks are assigned to which stations?
(e) What is the efficiency of the line obtained in part d?

Correct Answer:

verifed

Verified

blured image blured image (b) The cycle time is 180/30 = 6 hours...