Essay
A facility is trying to set up an assembly line, and has identified the various tasks, and their relationship to each other, as shown in the following table. Managers wish to produce 600 units per day, working two 8-hour shifts.
(a) Draw a network diagram of precedence relationships.
(b) Compute the required cycle time per unit in seconds.
(c) Compute the minimum number of workstations required to produce 600 units per day.
(d) Balance this line using the longest processing time heuristic.
(e) What is the efficiency of the line obtained in part (d)?
Correct Answer:

Verified
(a) The precedence diagram appears below...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q200: Which of Hackman and Oldham's five job
Q201: Standard time is always greater than normal
Q202: Work sampling estimates the percent of time
Q203: Sample observations of a claims processor made
Q204: An assembly line consists of 21 tasks
Q206: A bank manager wants to determine the
Q207: Suppose that the allowance factor for a
Q208: A work cell is required to make
Q209: The objective of warehouse layout is to
Q210: What design guidelines help retail layouts to