Multiple Choice
A firm is considering two location alternatives. At location A, fixed costs would be $4,000,000 per year, and variable costs $0.30 per unit. At alternative B, fixed costs would be $3,600,000 per year, with variable costs of $0.34 per unit. If annual demand is expected to be 9 million units, which plant offers the lowest total cost?
A) Plant A, because it is cheaper than Plant B for all volumes below 10,000,000 units.
B) Plant B, because it is cheaper than Plant A for all volumes below 10,000,000 units.
C) Plant A, because it is cheaper than Plant B for all volumes.
D) Plant B, because it has the lower variable cost per unit.
E) Neither Plant A nor Plant B, because the crossover point is at 9 million units.
Correct Answer:

Verified
Correct Answer:
Verified
Q173: Identify, in proper sequence, the steps in
Q174: Labor cost per unit is also referred
Q175: Possible states of nature found in capacity
Q176: When making a location decision at the
Q177: A school district is considering where in
Q179: Which of the following represents an aggressive
Q180: Manufacturers may want to locate close to
Q181: Advantage Milling Devices is preparing to buy
Q182: A useful tactic for increasing capacity is
Q183: For net present value calculations, we assume