Multiple Choice
Plots of sample ranges indicate that the most recent value is below the lower control limit. What course of action would you recommend?
A) Since there is no obvious pattern in the measurements, variability is in control.
B) One value outside the control limits is insufficient to warrant any action.
C) Lower than expected dispersion is a desirable condition; there is no reason to investigate.
D) The process is out of control; reject the last units produced.
E) Variation is not in control; investigate what created this condition.
Correct Answer:

Verified
Correct Answer:
Verified
Q16: A process is operating in such a
Q17: What is the difference between natural and
Q18: In acceptance sampling, a manager can reach
Q19: The term focused processes refers to the
Q20: An operating characteristic (OC) curve describes:<br>A) how
Q22: Which of the following is TRUE of
Q23: The strategy for improving service productivity that
Q24: The usual purpose of an R-chart is
Q25: A production process with only natural causes
Q26: Which of the following is TRUE regarding