A run test is used:
A) to examine variability in acceptance sampling plans.
B) in acceptance sampling to establish control.
C) to examine points in a control chart to check for natural variability.
D) to examine points in a control chart to check for nonrandom variability.
E) to test the validity of the Central Limit Theorem.