PDCA, developed by Shewhart, stands for which of the following?


A) Plan-Do-Check-Act
B) Plan-Develop-Check-Accept
C) Problem-Develop Solution-Check-Act
D) Problem-Do-Continue-Act
E) Prepare-Develop-Create-Assess

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q8: Identify the four costs of quality. Which

Q9: Which of the following is an example

Q10: Attribute inspection measures such dimensions as weight,

Q11: Which of the following refers to how

Q12: One of Britain's largest children's hospitals working

Q14: Three concepts that have proven helpful as

Q15: What does CSR stand for?<br>A) consumer sustainability

Q16: "The employee cannot produce products that on

Q17: Design for _ encourages designers to create

Q18: Suppose that a firm has made the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines