menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Operations Management Sustainability Study Set 4
  4. Exam
    Exam 3: Project Management
  5. Question
    An Activity on a PERT Network Has These Time Estimates
Solved

An Activity on a PERT Network Has These Time Estimates

Question 32

Question 32

Multiple Choice

An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. What is its expected activity time?


A) 2.00
B) 2.33
C) 2.67
D) 4.67
E) 14.00

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q27: The PERT pessimistic time estimate is an

Q28: What is a project organization?

Q29: PERT calculations typically include the duration variance

Q30: What are the three phases of a

Q31: One responsibility of a project manager is

Q33: An activity on a PERT network has

Q34: The main difference between PERT and CPM

Q35: What is the basic difference between PERT

Q36: A partially solved PERT problem is detailed

Q37: WBS stands for which of the following

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines