Multiple Choice
An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. What is its expected activity time?
A) 2.00
B) 2.33
C) 2.67
D) 4.67
E) 14.00
Correct Answer:

Verified
Correct Answer:
Verified