Which of the following quality control chart conditions is an indicator that the process is potentially out-of-control?
A) several consecutive data points between the UCL and the LCL
B) a data point below the LCL
C) a data point below the UCL
D) a data point in the outer 1/3 region
E) a data point on the center line