Multiple Choice
If a company spent less than predicted or spent an amount smaller than was budgeted, then it incurred a(an) :
A) positive variance.
B) negative variance.
C) equal variance.
D) fixed variance.
Correct Answer:

Verified
Correct Answer:
Verified