If a Company Spent More Than Predicted or Spent an Amount

Question 32

Multiple Choice

If a company spent more than predicted or spent an amount larger than was budgeted, then it incurred a(an) :


A) positive variance.
B) negative variance.
C) equal variance.
D) fixed variance.

Correct Answer:

verifed

Verified