Multiple Choice
The critical path on a PERT chart indicates:
A) The sequence of operations that are the most critical
B) The sequence of operations that require the shortest time for completion
C) The sequence of operations that are the most complicated
D) The sequence of operations that require the longest time for completion
Correct Answer:

Verified
Correct Answer:
Verified