Multiple Choice
Use the information below to answer the following question(s) .
Below is a spreadsheet for Trance Electronics.
Suppose that the project manager of Trance Electronics has identified the following uncertain variables in the model and the distributions and parameters that describe them, as follows:: normal with mean of 2,000,000 units and standard deviation of 400,000 units.
: uniform between $600,000,000 and $800,000,000.
: lognormal with mean of $150,000,000 and standard deviation $30,000,000.
: triangular with minimum = 2%, maximum = 6%, and most likely = 3%.
: triangular with minimum = 15%, maximum = 25%, and most likely = 20%.
The number of trials per simulation is equal to 10,000 at a Sim.Random Seed of 2.Run the simulation and answer the following questions using the Risk Solver Platform.
-What is the expected loss ratio obtained from the simulation results of the net present value?
A) 93.50%
B) 72.45%
C) 67.32%
D) 85.42%
Correct Answer:

Verified
Correct Answer:
Verified
Q19: Answer the following question(s) using the
Q20: Conduct Monte Carlo simulation using historical
Q30: Use the information below to answer the
Q31: Use the information below to answer
Q32: Use the information below to answer
Q34: Use the information below to answer
Q36: Which of the following is a parameter
Q41: The Risk Solver Platform feature allows you
Q48: Answer the following question(s) using the
Q49: Explain the concept of the "flaw of