Multiple Choice
Which of the following was the result in Fostveit v. Poplin the case in the text involving the right of a contractor who had built storage units to place a lien on the property in which "substantial performance" has occurred according to a contract?
A) The court found that a lien was able to be placed on a property because Fostveit had substantially performed his portion of the work assigned to him pursuant to the parties' contract.
B) The court found that a lien not allowed to be placed on the property because Fostveit had multiple violations of building codes.
C) The court found that a lien was allowed on the property, but only after Fostveit remedied the building code violations in compliance with local law.
D) The court found that a lien was not available because the Poplin's had improved the property pursuant to the contract and a lien would be inequitable.
E) The court found that a lien was available but the materials and time associated with the improvements the Poplin's had made would need to be deducted from the lien amount.
Correct Answer:

Verified
Correct Answer:
Verified
Q44: Which of the following is false regarding
Q45: Ridland has had severe problems staying out
Q46: When considering whether a secured party or
Q47: [Defective Windows] Cecelia hired a contractor, Paul,
Q48: A(n) _ permits a debtor to retain
Q50: A creditor has a secured interest in
Q51: When can a creditor seek a writ
Q52: Which of the following statements accurately describes
Q53: [Bad Hair Day] Tara started a new
Q54: After judgment is entered against Kylie in