Solved

Which of the Following Was the Result in Fostveit V

Question 49

Multiple Choice

Which of the following was the result in Fostveit v. Poplin the case in the text involving the right of a contractor who had built storage units to place a lien on the property in which "substantial performance" has occurred according to a contract?


A) The court found that a lien was able to be placed on a property because Fostveit had substantially performed his portion of the work assigned to him pursuant to the parties' contract.
B) The court found that a lien not allowed to be placed on the property because Fostveit had multiple violations of building codes.
C) The court found that a lien was allowed on the property, but only after Fostveit remedied the building code violations in compliance with local law.
D) The court found that a lien was not available because the Poplin's had improved the property pursuant to the contract and a lien would be inequitable.
E) The court found that a lien was available but the materials and time associated with the improvements the Poplin's had made would need to be deducted from the lien amount.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions