Multiple Choice
The critical path is
A) a sequence of large cash outflows.
B) a sequence of large cash inflows.
C) the set of extremely large cash outflows at the very beginning of a project's lifecycle.
D) the set of activities that must be completed on time in order to keep the project on schedule.
E) the set of extremely large cash outflows at the very end of a project's lifecycle.
Correct Answer: