Multiple Choice
A city council is planning to build a new bridge across a creek. This will require an immediate expenditure of $50 000, but will save citizens an estimated $5 000 in travel costs every year over the next twenty years. If the council's MARR is 5%, what is the BCR for the project?
A) 0.1
B) 1.25
C) 1.44
D) 1.64
E) 2.00
Correct Answer:

Verified
Correct Answer:
Verified