Multiple Choice
A construction contractor finished a bridge across a river 12 months early and received more than $5 million for the early completion. This is an example of reducing project duration caused by
A) imposed project deadlines.
B) time to market.
C) unforeseen project delays.
D) high overhead.
E) incentive contracts.
Correct Answer:

Verified
Correct Answer:
Verified