Multiple Choice
When looking at the critical path for a delayed project and the project manager sees that adding resources will reduce or remove the delay, the project manager knows that the project is:
A) Over Allocated.
B) Time-Constrained.
C) Institutionally Challenged.
D) Ahead of schedule.
E) Unstable.
Correct Answer:

Verified
Correct Answer:
Verified