Multiple Choice
Funds that are for identified risks that have a low probability of occurring and that decrease as the project progresses are called ______ reserves.
A) management
B) unidentified risk
C) contingency
D) padded
E) just in case
Correct Answer:

Verified
Correct Answer:
Verified