Multiple Choice
When considering risk response development, assuming the risk because the chance of such an event is slim is known as _________ the risk.
A) transferring
B) mitigating
C) avoiding
D) retaining
E) escalating
Correct Answer:

Verified
Correct Answer:
Verified