Multiple Choice
The backward pass in project network calculations determines all of the following EXCEPT
A) latest time an activity can begin.
B) earliest time an activity can finish.
C) the critical path.
D) how long an activity can be delayed.
E) latest time an activity can finish.
Correct Answer: