Solved

The Backward Pass in Project Network Calculations Determines All of the Following

Question 78

Multiple Choice

The backward pass in project network calculations determines all of the following EXCEPT


A) latest time an activity can begin.
B) earliest time an activity can finish.
C) the critical path.
D) how long an activity can be delayed.
E) latest time an activity can finish.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions