Multiple Choice
The assumption that all immediately preceding activities must be 100% complete is too restrictive in some situations. When an activity is broken down into smaller segments in order to start the succeeding activity sooner, this is called
A) hammock activities.
B) concurrent engineering.
C) a forward pass.
D) dissecting.
E) laddering.
Correct Answer: