Which of the following does NOT help describe a bottom-up estimating approach?
A) They are made by someone who uses experience and / or information from someone else to determine overall project cost and duration.
B) They establish low-cost, efficient methods for completing activities.
C) They typically come from the people actually doing the work and who are most knowledgeable about the task at hand.
D) Estimates are made at the work package level and then "rolled up" to determine estimates for major deliverables and for the project itself.
E) They can take place after the project has been planned in detail.
Correct Answer:

Verified
Correct Answer:
Verified
Q44: Which of the following would best represent
Q45: Identify and briefly describe three out of
Q46: Repetition of a task generally results in
Q47: Identify the drawbacks to an excessive detail
Q48: The consensus method of estimating costs is
Q50: Top-down estimates usually are derived from someone
Q51: Describe phase estimating. When should it be
Q52: The salary of the project manager and
Q53: List and briefly describe four reasons why
Q54: Work package estimates should include allowances for