Multiple Choice
When work package estimates are made by individuals most knowledgeable about the work being performed and these estimates are then "rolled up" to find estimated costs for major deliverables and the project itself, ____________ estimating is being used.
A) top-down
B) analogous
C) bottom-up
D) reference class
E) professional estimation
Correct Answer:

Verified
Correct Answer:
Verified
Q38: If a project is internal to the
Q39: List and briefly explain two reasons why
Q40: Typical kinds of costs found in a
Q41: All task time estimates need consistent time
Q42: Estimating can be challenged by<br>A) human nature.<br>B)
Q44: Which of the following would best represent
Q45: Identify and briefly describe three out of
Q46: Repetition of a task generally results in
Q47: Identify the drawbacks to an excessive detail
Q48: The consensus method of estimating costs is