Multiple Choice
The estimating factor that considers the decreasing accuracy of estimates as one forecasts activities that are further into the future is known as ____________.
A) project complexity
B) planning horizon
C) people
D) organizational culture
E) padding estimates
Correct Answer:

Verified
Correct Answer:
Verified