Multiple Choice
Consider a five-mile-long railroad tunnel. Tunnel experts and advocates estimate the total cost to be $200 million. What is the reference class for this project? But reference class projects in this area have been over-budget by 30%. So, what should the actual revised budget number be for this proposed five-mile tunnel project?
A) Past bridge projects, $230 million
B) Past tunnel projects, $260 million
C) Past highway projects, $200 million
D) Past building projects, $230 million
E) Past construction projects, $230 million
Correct Answer:

Verified
Correct Answer:
Verified
Q17: A project estimator is working on estimates
Q18: One guideline to follow when estimating time,
Q19: Which of the following is NOT one
Q20: Costs that are not directly related to
Q21: Which of the following is NOT one
Q23: Project managers typically use _, also called
Q24: In practice, estimating processes are frequently classified
Q25: A way to improve estimates on future
Q26: Project costs such as labor and materials
Q27: The salary of the project manager would