You Have Just Been Given a Project That Has a Specific

Question 61

Multiple Choice

You have just been given a project that has a specific completion date. After a discussion with top management you find that while the date is important the cost is more important and a slip in delivery would be acceptable if required to meet the cost targets. The completion date is best classified as


A) constrained.
B) reduced.
C) accepted.
D) limited.
E) optional.

Correct Answer: