    The Highest Element in the Hierarchical Breakdown of the WBS
Solved

The Highest Element in the Hierarchical Breakdown of the WBS

Question 99

Question 99

Multiple Choice

The highest element in the hierarchical breakdown of the WBS is


A) a work package.
B) sub-deliverables.
C) a cost account.
D) major deliverables.
E) the project.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q94: Which of the following items has to

Q95: The gradual expansion of project requirements, specifications

Q96: The WBS is best suited for design

Q97: A project professional is viewing a document

Q98: Describe as many different ways to define

Q100: Taking advantage of opportunities to reduce costs

Q101: The type of information that will need

Q102: What is a work package and what

Q103: Creating a communication plan typically follows a

Q104: In many cases, the causes of scope

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines