In Making Project Trade-Offs, a Criterion That Is Allowed Not

Question 36

Multiple Choice

In making project trade-offs, a criterion that is allowed not to meet the original target, for example, allowing the schedule to slip, is classified as ___________.


A) enhanced
B) accepted
C) constrained
D) static
E) unchangeable