Multiple Choice
In making project trade-offs, a criterion that is allowed not to meet the original target, for example, allowing the schedule to slip, is classified as ___________.
A) enhanced
B) accepted
C) constrained
D) static
E) unchangeable
Correct Answer:

Verified
Correct Answer:
Verified