When Specific Work Packages Are Assigned to a Particular Group

Question 108

Multiple Choice

When specific work packages are assigned to a particular group or person within the organization, the result is called a(n) ___________.


A) work breakdown structure
B) process breakdown structure
C) organization breakdown structure
D) project priority matrix
E) responsibility matrix