A Project Manager Is Considering How to Structure a Project

Question 77

Multiple Choice

A project manager is considering how to structure a project team that will not directly disrupt ongoing operations. The project needs to be done quickly and a high level of motivation will be needed in order to do that. For this situation, the ______ organization would be the best choice.


A) functional
B) balanced matrix
C) weak matrix
D) strong matrix
E) projectized

Correct Answer: