Multiple Choice
High project costs and difficult post-project transition are two evident weaknesses of a(n) __________ organization.
A) dedicated project team
B) weak matrix
C) strong matrix
D) functional
E) projectized
Correct Answer:

Verified
Correct Answer:
Verified