Multiple Choice
Agile project management involves ____ whereas traditional project management involves _______.
A) iterative and incremental delivery, upfront planning with high predictability
B) high certainty, projects with unstable scope
C) high uncertainty, projects with unknown requirements
D) known and stable scope, unknown requirements
E) projects with high predictability, project with unknown or unstable requirements
Correct Answer:

Verified
Correct Answer:
Verified