Scrum uses a series of coordinated meetings to manage the development process. Which of the following is held at the start of each sprint? During this meeting the product owner and development team negotiate which product backlog items the team will attempt during the next sprint.


A) Sprint planning meeting
B) Release planning meeting
C) Sprint review meeting
D) Daily Scrum meeting
E) Sprint retrospective meeting