Because of Circumstances Beyond the Control of the Project Team

Question 66

Multiple Choice

Because of circumstances beyond the control of the project team, many projects are easy for a review group to close down. This type of project closure is called


A) normal.
B) premature.
C) perpetual.
D) failed project.
E) changed priority.