Multiple Choice
Which of the following is not a major activity associated with project closure?
A) Getting delivery acceptance from the customer.
B) Shutting down resources and releasing to new uses.
C) Returning project players to an 'on the beach' status.
D) Closing accounts and seeing that all bills are paid.
E) Delivering the project to the customer.
Correct Answer:

Verified
Correct Answer:
Verified