The Final Step in the Project Control Process for Measuring

Question 10

Multiple Choice

The final step in the project control process for measuring and evaluating project performance is to


A) take appropriate action.
B) prepare a report to top management.
C) follow up on corrective action.
D) measure progress and performance.
E) review spending with team members.

Correct Answer: