    Given That the AC = 500, PV = 400 and EV
Solved

Given That the AC = 500, PV = 400 and EV

Question 17

Question 17

Multiple Choice

Given that the AC = 500, PV = 400 and EV = 300, this project is currently _________ budget and ______ schedule.


A) under, ahead of
B) under, behind
C) over, behind
D) over, ahead of
E) on, on

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q12: The only accurate method for determining the

Q13: Because of their easy-to-understand visual format, tracking

Q14: The PV, AC and CV are all

Q15: The _ variance is the difference between

Q16: The _ rule assumes credit is earned

Q18: The indicator that tells you the amount

Q19: Baseline project budgets are derived from time-phasing

Q20: The value that tells you the planned

Q21: A project manager receives the following information

Q22: What is a "rubber baseline" and how

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines