Multiple Choice
Outsourced projects are susceptible to conflicts since people are unaccustomed to working together. Which of the following is a primary control mechanism for dealing with and resolving problems?
A) Arbitration
B) Escalation
C) Collaboration
D) Mediation
E) Regulation
Correct Answer:

Verified