A _____ cannot be started until a previous task is completed.


A) dependent task
B) predecessor task
C) precursor task
D) concurrent task

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q41: In addition to tasks,every project has events,or

Q42: A _ chart displays complex task patterns

Q43: A project manager should never develop time

Q44: Adding more people to a project actually

Q45: A _ consists of horizontal bars,connected with

Q47: Generally,systems analysts review the work of other

Q48: The three legs of the project triangle

Q49: A _ is a proactive effort to

Q50: Program Evaluation Review Technique (PERT)/Critical Path Method

Q51: If the project manager fails to plan,staff,organize,supervise,communicate,motivate,evaluate,direct,and

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines