What Is the Final Step in Establishing an Implementation Timetable

Question 139

Multiple Choice

What is the final step in establishing an implementation timetable?


A) Assigning responsibility for completing each activity
B) Organizing activities in their proper order
C) Determining time required for completion
D) Identifying the activities to be performed
E) Separating activities to be performed in sequence from those performed simultaneously

Correct Answer: