Multiple Choice
The risk of concluding control risk is lower than it actually is, is also known as:
A) risk of overreliance.
B) risk of underreliance.
C) risk of incorrect acceptance.
D) risk of incorrect rejection.
Correct Answer:

Verified
Correct Answer:
Verified