Multiple Choice
Eads Industrial Systems Company (EISC) is trying to decide between two different conveyor belt systems.System A costs $427,000,has a 6-year life,and requires $115,000 in pretax annual operating costs.System B costs $502,000,has an 8-year life,and requires $79,000 in pretax annual operating costs.Both systems are to be depreciated straight-line to zero over their lives and will have a zero salvage value.Whichever system is chosen,it will not be replaced when it wears out.The tax rate is 33 percent and the discount rate is 24 percent.Which system should the firm choose and why?
A) A; The net present value is $211,516.
B) A; The net present value is -$588,792.
C) A; The net present value is -$314,216.
D) B; The net present value is $308,222.
E) B: The net present value is -$612,240.
Correct Answer:

Verified
Correct Answer:
Verified
Q41: You are considering the purchase of a
Q42: Which one of the following will increase
Q43: Heer Enterprises needs someone to supply it
Q44: The Card Shoppe needs to maintain 20
Q45: The annual annuity stream of payments that
Q47: The equivalent annual cost considers which of
Q48: Which one of the following best illustrates
Q49: Net working capital:<br>A)can be ignored in project
Q50: Marie's Fashions is considering a project that
Q94: The operating cash flow of a cost-cutting