Multiple Choice
Which of the following is most closely associated with the output of a project becoming a standard part of the operating systems of the sponsoring firm or client?
A) termination-by-addition
B) termination-by-extinction
C) termination-by-integration
D) termination-by-starvation
E) termination-by-elimination
Correct Answer:

Verified
Correct Answer:
Verified