In the Traditional Waterfall Approach, When a Project Is Evaluated

Question 30

True/False

In the traditional waterfall approach, when a project is evaluated to be 90% complete this typically means that there is 90% progress toward completing the project but likely 0% is actually completed and operational.

Correct Answer: