Multiple Choice
Renly, a project manager in a construction company, has undertaken a project to construct a house. He estimates that the house will take 5 months to complete with his team of 10 workers. He also prepares a second estimate that allows the house to be completed in 2 months if 10 more workers are added to the team. Renly's second estimate is referred to as the _____.
A) crash duration
B) standard duration
C) slope duration
D) buffer duration
E) critical duration